Allied Health JTED Health Occupation Program facilities going up
The Allied Health JTED Health Occupation program facilities at the Prescott Valley Center are going up. As photos posted in the District Governing Board Agenda show, two of which are below, the construction crews are already working on the second floor of the new structure.
The goal of the construction and design team is to ensure that classroom and lab spaces are ready for students at the start of the fall 2017 semester.
The construction program dates for completion as outlined by the College is as follows:
-
Prescott Valley Center Parking Expansion – December 2016 through June 2017
-
Prescott Valley Center Addition – January 2017 through July/August 2017
-
Prescott Valley Center Addition Floor 2 Completion – December 2017
-
Building 2 Interior Remodel – May through August 2017
-
Prescott Valley Center Existing Space Remodel – May through August 2017
-
Move JTED from Centre Pointe to Prescott Valley – July/August 2017
-
Move Allied Health to Prescott Valley Center – July/August 2017