Pandemic has apparently not slowed efforts of goal to get Building “L” ready by fall 2020
The April Yavapai Community College Facilities Management Newsletter reports that construction on Building “L” on the Verde Campus is moving ahead. According to the report, a “ new roof is installed, and the building is very close to being completely dried in. Electrical transfer occurred during spring break, so the building is now tied into the campus with the new service. All structural steel for the new entrance is complete along with concrete and exterior walls. Painting of the exterior metal features is underway.”
The report goes on to say that “the interior of the building on the first floor, concrete polishing and staining is in process along with painting of walls and door jambs. Lighting is being installed throughout the first and second floors. On the second floor, drywall is nearing completion, and the walls are being prepped for paint.”