The classrooms, offices, etc. that will house ASU Bachelor’s programs are about finished
With more than $2 million already spent in the overall improvements of the first floor of the Prescott Valley expansion, the College is completing the second floor. The estimated cost for the second floor renovation/construction is around $1.57 million. As of the November Governing Board meeting, furniture is being installed along with technology on the second floor.
The final phase of construction will begin December 17 and will include renovating the garage portion of the Prescott Valley Center for student development functions, the locker room which will become a science lab, classroom conversion to a lab or Imaging (Radiology Technology) and renovating the rotunda area for Zoom and student lounge spaces. Completion of this phase of construction is scheduled for June 15, 2019.
The following are some photos of the second floor construction provided the Governing Board by the College management team in the Board agenda at the November 2018 meeting.